CASE STUDY 03 · ALBERTA · TRANSMISSION PIPELINES
Post-remediation CIS and DC interference study
Close interval and DC interference surveys on two parallel transmission pipelines at ten rectifier sites, after the owner separated its lines from a shared CP system.
Transmission pipeline operator
- Stray current and interference
- Close interval survey
- Cathodic Protection
The problem
A pipeline operator had separated the negative drain cables of two parallel pipelines from a neighbouring operator's rectifiers at multiple sites, and installed dedicated junction boxes, variable resistors and remote monitoring. It needed to know how its CP systems were performing after the change, and what DC interference the change caused on its own lines and on other structures.
What we did
- 01Survey each rectifier siteClose interval surveys ran from each of ten rectifier locations to the upstream and downstream test stations on the lines at each site, with waveforms at set locations and drain, bond and rectifier readings recorded.
- 02Stop when the data did not fitEarly interruption tests showed current still reaching one line despite the planned interruption set-up. Rather than collect unrepresentative data, the crew paused the survey plan.
- 03Map the current firstThe team mapped current and identified its sources, verified interruption coordination among the influencing rectifiers, checked bond, drain and sacrificial anode influences, and worked through the findings with the owner and third parties. This added about one week of field work, raised with the owner as a cost summary.
- 04Complete every siteAll CIS runs were completed at all ten sites, with extra test station and junction box current readings captured along the way.
- 05Explain what the lines are doingThe working theory for the reverse IR shifts on both lines is voltage gradients from older parallel pipelines rather than meaningful current discharge. OFF potentials are generally high and not yet fully explained; remaining magnesium anodes are one suspect. On one line, the current mapping gave confidence that no negative drains had been missed.
- 06Turn data into design inputsPreliminary findings reached the owner five days after demobilizing, and the full field data package two days after the review meeting. Separating the systems appears feasible, and the two lines could potentially run as one independent CP system with interference bonds, the basis for the owner's planned dedicated CP system.