CASE STUDY 08 · ALBERTA · MUNICIPAL WASTEWATER

CP design for a trunk sewer creek crossing

An impressed current CP design for a new coated steel trunk sewer that crosses a creek and wetland, held down by 37 bare-steel buoyancy straps that set the current demand.

Municipal wastewater owner · via its engineering consultant

  • Cathodic Protection
  • CP design
  • Wastewater
~200 m
Crossing between manholes, about half in wetland
37
Buoyancy control straps in the design
6 A
Design current, up to (15 mA/m²)
2
Monitoring coupons, with a reference electrode

The problem

A new 1.95 m steel trunk sewer, externally coated, crosses a creek about 200 m between manholes, about 100 m of it in wetland. Bare-steel buoyancy control straps hold it down, and they raise the cathodic protection current demand far beyond what the coated pipe alone needs. The system also had to go in the open excavation just before backfill.

Profile of a coated steel trunk sewer crossing a creek and wetland between two manholes, about 200 m: 37 buoyancy straps, a linear MMO anode along the ballast, a rectifier, two coupons with a reference and a test station; up to 6 A at 15 mA/m².

What we did

  1. 01
    Start from the civil design
    The plan and profile, the anti-buoyancy ballast details and the ballast sketch were reviewed to find every piece of steel the CP system has to protect.
  2. 02
    Size the current
    About 1 m² of exposed steel per strap assembly at 15 mA/m² gives a total requirement of up to 6 A, more than sacrificial anodes can deliver.
  3. 03
    Design impressed current
    A flexible MMO linear anode runs along the ballast slabs, sized for about 7 mA/m over the life of the system at roughly 3 m strap spacing.
  4. 04
    Build in monitoring and bonding
    A stationary reference electrode, two 10 cm² coupons and a two-wire test station at the far manhole; strap weld plates loop-bonded with pin-brazed jumpers, and every braze connection coated.
  5. 05
    Issue for construction
    The design report and drawing set (plot, elevations, details and pin brazing) were issued for construction, with what the owner must confirm: support details, power at the rectifier, and an installation schedule set with ACiD.

Have a similar asset?

Tell us about the main, line or structure. An engineer reads every request, and anything that needs a stamp goes to one of our Professional Engineers.

Have an asset that needs protecting?
Request a quote
AMPP CP Level 4ISNetworldAvettaComplyWorks